An injection molding sample run is useful when the buyer and supplier agree what the run must prove, which configuration will be tested and how the samples will be accepted. A trial is not a substitute for a released specification or production plan.
Six essentials for a decision-ready sample run
| Thiết yếu | Agree before the run | Record after the run |
|---|---|---|
| 1. Trial purpose | Whether the trial evaluates tool function, fill, dimensions, appearance, assembly or another defined question | Purpose, open questions and the decision owner |
| 2. Released inputs | Part and mold revisions, resin grade, color, machine and any approved options | Configuration, material lot and deviations |
| 3. Run plan | Planned sequence, sample count, cavity identification and which process records will be captured | Shot or run records, time, machine and responsible personnel |
| 4. Measurement plan | Critical dimensions, appearance criteria, assembly checks, method and measurement timing | Results by cavity and sample, including measurement equipment where applicable |
| 5. Acceptance criteria | Pass/fail limits, permitted deviations, retest rules and required approvals | Approved result, deviations and decision record |
| 6. Corrective action | How issues are assigned, contained, changed and rechecked | Owner, due date, change revision and closure evidence |
Keep the trial configuration traceable
Label samples with the part revision, mold and cavity where applicable, material lot and run date. Keep the approved criteria with the result so that the buyer and supplier compare the same configuration. If a process, material, tool or part revision changes, document whether the affected checks must be repeated.
Separate sample approval from production release
A successful sample answers the questions included in its trial plan. It does not automatically establish long-term process capability, production capacity or unchanged performance after a later revision. Define any further pilot, qualification or ongoing monitoring work in the project agreement.
For related review topics, see injection molding process-control checks, mold-quality assessment checklist và mold-processing evidence.
Các câu hỏi thường gặp
Should the acceptance criteria be written after seeing the samples?
Set criteria before the run wherever possible. If the project learns that a criterion needs revision, document the change, approval and effect on the existing samples.
Does one successful sample prove production quality?
No. It proves only the agreed checks for that sample and configuration. The buyer and supplier should define any additional process, capacity or production-release evidence required.